WHAT’S HAPPENING ON THE GROUND
Waikōwhai is part of the wider Roskill Development, led by Kāinga Ora - Homes and Communities, focused on delivering high-quality new homes alongside upgrades to parks and essential infrastructure.
When complete, the Waikōwhai neighbourhood will deliver over 708 brand-new homes.
PROGRESS SO FAR
- Physical works for Stages 1 and 2 are now complete, enabling around 380 new homes. This includes 23 social homes. All market land within these stages has been contracted to seven development partners.
HOMES UNDER CONSTRUCTION
- House construction is progressing really well for the first two market superlots, yielding 43 homes. These are due for completion around Q3 of 2026. These homes are currently available to purchase. More market homes are due to commence construction this year, which will also be available to purchase. Plenty more homes are to commence construction in 2026.
PARKS, INFRASTRUCTURE AND UPGRADES
- Work has commenced on Te Auaunga ki Tai reserve, an extension of Molley Green Reserve. House removals, land remediation and wastewater connection to the Central Interceptor are complete. The project provides critical stormwater and wastewater upgrades and continues to celebrate the daylighting of the awa, with completion anticipated around the end of 2026.
STREETS AND INFRASTRUCTURE READY FOR GROWTH
- Stage 4 and 4B house removals are due to start Q2 of 2026, followed by civil construction. This will enable approximately 145 social homes and around 100 market homes.
LOOKING AHEAD
Waikōwhai continues to move forward as a well-connected, future-ready neighbourhood, with homes, parks and infrastructure taking shape together. Thank you to all in the community who have shared their time and input.
TIMELINE
Autumn 2026
- First market homes continue construction.
- More market homes are to commence construction and are available to purchase.
- Stage 4 and 4 B house removals commence.
Winter 2026
- Te Auaunga ki Tai Reserve works continue.
- Stage 4 and 4B civil works commence.
- First market homes completed.
Spring 2026
- More market homes to commence construction.
- Te Auaunga ki Tai Reserve works are expected to be completed.
TOTAL HOMES (by stage)
| NEW HOMES | STAGE 1 | STAGE 2 | STAGE 3 | STAGE 4 | TOTALS |
| SOCIAL | 18 | 5 | 0 | 145 | 168 |
| MARKET | 123 | 235 | 78 | 104 | 540 |
| TOTAL | 141 | 240 | 78 | 249 | 708 |
HOMES FOR SALE
From first homes to forever homes – there are all sorts of beautiful, brand new, high-quality houses for sale in Roskill Development. See all of the homes for sale right now, right here.
WANT TO KNOW MORE?
Click here to learn more about Waikōwhai or get in touch. Or pop in for an in-person chat with one of the team. Roskill Development has an information centre at 142 May Road, Roskill South, which is open Wednesday to Saturday between 10am – 4pm. Walk-ins welcome, or you can make a booking.